Assembly Cost Calculator
Assembly cost is almost entirely time multiplied by a rate. This calculator splits the unit into handling, fastening, inspection and rework minutes, adds fixture amortisation and consumables, then applies a yield uplift so the number can be compared with a supplier quote.
Effective time — min/unit · Output — units/hour · Labour share —%
Range ±25%. Cycle time is the hardest input to pin down: the same station can differ by 30% between an experienced operator and a new hire, and awkward part orientation, taped cabling or wide incoming tolerances all add minutes. The model stacks handling time linearly with part count and does not judge assembility — that is exactly where the ±25% comes from.
How the number is built
- Handling and alignment — part count times seconds per part. This is the floor of assembly labour; more parts and stronger orientation bias push it up quickly.
- Fastening and gluing — screws, clips, adhesive beads and cable routing are fixed blocks of time per unit, not linear in part count.
- Inspection — functional test, visual check and burn-in all consume operator minutes, usually at a higher grade than assembly itself.
- Rework — rework rate times rework minutes enters the labour; the reworked unit also ties up material and labour twice, which shows up in the yield factor.
- Fixture amortisation — jigs, work-holding and test fixtures divided by their service life. Low volume makes this line large.
- Scrap uplift — scrapped units still consume material, labour and consumables. Cost per good unit is therefore divided by (1 − scrap rate).
Formulas
handling min = parts × seconds per part ÷ 60
rework min = rework rate × rework minutes
effective min = handling + fastening + inspection + rework
labour = effective min ÷ 60 × rate
fixture = fixture cost ÷ fixture life
subtotal = labour + fixture + consumables + components
scrap uplift = subtotal × scrap ÷ (1 − scrap)
unit cost = subtotal + scrap uplift Worked example
A 12-part control-board assembly: 8 seconds handling per part, 2.4 minutes fastening and routing, 0.5 minutes test, 5% rework at 3 minutes, labour at 45 CNY/hour, a 3,000 CNY fixture good for 20,000 units, 0.20 CNY consumables and 2% scrap:
| Handling 1.60 + fastening 2.40 + test 0.50 + rework 0.15 = 4.65 min | 4.65 min |
| Labour (4.65 ÷ 60 × 45) | ¥3.49 |
| Fixture (3,000 ÷ 20,000) | ¥0.15 |
| Consumables | ¥0.20 |
| Scrap uplift (3.84 × 2 ÷ 98) | ¥0.08 |
| Total | ¥3.92 per unit (about 12.9 units/hour) |
Replace the fixture with an 80,000 CNY semi-automatic line and the cycle drops to 1.8 minutes, so labour falls to 1.35 CNY — but amortising 80,000 over 20,000 units adds 4.00 CNY per unit and the part becomes more expensive. Automation only pays when annual volume is high enough to spread the tooling over hundreds of thousands of units.
Where to attack the cost
Read the labour share first. Above 60% means cycle time dominates: simplify the structure — fewer screws, snap fits, symmetrical parts that cannot be oriented wrong — and the saving usually beats buying equipment. Fixture amortisation above 10% means the batch is too small; merge batches or use general-purpose work holding. Consumables look trivial but glue and labels routinely run 5–15% of assembly cost, especially where dispense volume is uncontrolled.
Not included
- Packaging and cartoning (see the packaging calculator) and outbound freight
- Equipment depreciation and factory rent, which sit inside the loaded labour rate
- Incoming inspection (IQC) and supplier quality cost
- Training, certification and line-down losses
- Warranty accrual and field returns
FAQ
Why is the labour rate not the wage?
An operator may take home 25 CNY/hour while the employer pays 35–50: social insurance adds roughly 30%, plus team leaders, quality, stores and factory overhead. Quotes always use the loaded rate; costing from the wage alone understates assembly by about half.
How do I estimate cycle time?
Time the station 30 times and take the median, not the fastest run. Without a line, break the motion down with MTM-style values: reach and grasp 0.3–0.6 s, align 1–3 s, drive one screw 4–8 s by hand. Products with keyed connectors, flex cable or cable dressing typically run 1.5× the paper estimate.
What rework rate is realistic?
Mature consumer-electronics lines run 95–99% first-pass yield, so 1–5% rework; 10–20% is normal during a new-product pilot. Rework costs more than the extra minutes: cosmetic damage and second-time scrap are not in this model.
Why divide by (1 − scrap rate)?
To ship 100 good units you must start about 102 at 2% scrap. Those extra units consume material, labour and consumables just the same, so spreading them over the good units raises unit cost. The effect matters most on high-value parts and large batches.