Die casting differs from injection molding in one important way: you pay for the shot, not the part. Runner metal, cycle time per shot and mold life in shots all drive the price.

¥— per part
Alloy (shot weight)
—
Machine time
—
Mold amortisation
—
Deburring
—

Cycle — s · shot weight — g

Accuracy: ±30%. Cycle time depends heavily on the machine tonnage, die temperature control and spray routine. Thin walls and long flow paths push it up sharply.

Why die casting is priced per shot

Formula

net_weight      = volume × density
shot_per_part   = net_weight × (1 + runner_ratio)
material        = shot_per_part / 1000 × price_per_kg / (1 − scrap)

cycle_time      = 20 + 3 × wall_mm + 0.5 × √volume
machine         = cycle / 3600 / cavities × rate / (1 − scrap)

mold            = mold_cost / life_shots / cavities / (1 − scrap)
total           = material + machine + mold + deburring

Worked example

ADC12, 100 cm³, 3 mm wall, 2 cavities, 5% scrap, 8% runner, ¥300k die over 100k shots:

Net weight 270 g; shot 291.6 g → 306.9 g after scrap—
Alloy at ¥19/kg¥5.83
Cycle 34 s ÷ 2 cavities at ¥150/h¥0.75
Mold ¥300,000 ÷ 100,000 shots ÷ 2¥1.58
Deburring¥1.50
Total per part¥9.66

Alloy is 60% of the cost here. Switch the same part to ZAMAK 3 and the material line more than doubles, because zinc is 2.4× denser than aluminium and only 26% cheaper per kilo.

What this does not include

FAQ

Die casting or gravity casting?

Die casting wins above roughly 3,000–5,000 parts per year, where the die cost amortises and the cycle advantage pays. Below that, gravity or sand casting with an inexpensive pattern is usually cheaper, and machining from billet may beat both.

How many cavities should the die have?

Fewer than you would think: two to four is typical. A die with many cavities costs more, takes longer to build, and is harder to keep balanced. Because die life is counted in shots, more cavities also means fewer shots per part — the amortisation benefit is smaller than for injection molding.

Why does my quote show a much higher scrap rate?

Thin walls, long flow paths, tight porosity requirements and cosmetic surfaces all push real scrap up. Suppliers often quote 5–10% for robust parts and 15–25% for difficult ones. Ask what rate they used — it moves the price more than the alloy price does.