FOB Price Calculator
A part that leaves the factory at 12.50 CNY quotes at 14.14 CNY FOB. The 1.64 CNY between them is inland freight, customs, port charges, booking and markup. This tool itemises each line and returns both the CNY and USD price.
| Cost including pre-shipment charges | — CNY/part |
| Pre-shipment charges | — CNY/part |
| Markup | — CNY/part |
| Batch FOB value | — USD |
| Charges / markup share of FOB | —% / —% |
Rates and charges move. This tool does not hedge or forecast FX, and it excludes export rebates, VAT and commissions. Use the rate and charge list your finance team signs off — once a FOB price is quoted, exchange-rate movement is your cost.
What FOB includes
- Included — goods cost, inland freight to port, customs and documents, port charges and THC, booking and loading.
- Excluded — ocean freight, insurance, destination charges (those are CFR or CIF), import duty and clearance.
- The line — risk transfers when the goods are on board the vessel (Incoterms 2020 wording); everything after that is the buyer's cost.
The most common error is adding ocean freight into FOB: the buyer then treats it as CIF and discovers a container's worth of freight is missing. The opposite error — quoting ex-works as FOB — leaves you paying port and customs charges yourself.
Formulas
pre-shipment charges = inland + customs + port + booking
charge per part = charges ÷ batch pieces
cost per part = ex-works + charge per part
markup = cost per part × markup rate
FOB price = cost per part + markup
USD price = FOB price ÷ exchange rate Worked example
Ex-works 12.50 CNY, 5,000 pieces, charges 800 + 350 + 1,200 + 600 = 2,950 CNY, 8% markup, rate 7.10:
| Charge per part (2,950 ÷ 5,000) | 0.59 CNY |
| Cost (12.50 + 0.59) | 13.09 CNY |
| Markup (13.09 × 8%) | 1.05 CNY |
| FOB price | 14.14 CNY ≈ $1.9915 |
| Batch value | $9,957.75 |
Drop the batch to 500 pieces and the same 2,950 CNY spreads over 500 units: 5.90 CNY each, FOB jumps to 19.87 CNY — 41% higher. That is why small export orders struggle: pre-shipment charges are fixed, and fewer pieces make each one carry more.
Markup is not gross margin
Markup works on cost: price = cost × (1 + markup). Gross margin works on price: profit ÷ price. A 20% markup is a 16.7% gross margin (0.2 ÷ 1.2), not 20%. Sales teams quote markup, finance reports margin, and three to four points of profit disappear in the gap.
gross margin = markup ÷ (1 + markup)
markup = gross margin ÷ (1 − gross margin) Four things that get missed
- Export rebate — the refund rate differs from the VAT rate and effectively lowers ex-works cost; quoting FOB off a VAT-inclusive price overstates it.
- Bank charges and commission — L/C, collections and agent commission usually run 0.5–3%.
- Export packing and pallets — crates, fumigation and pallets are often billed separately (see the packaging calculator).
- FX buffer — a quote valid 30 days can lose 2% to the exchange rate, which is half your markup.
FAQ
How far apart are FOB and CIF?
By ocean freight and insurance. A 40HQ to Europe in peak season can run $3,000–6,000, which on 5,000 pieces is $0.60–1.20 each — 30–50% on top of a small FOB price. The two numbers for the same product barely resemble each other.
Why is the USD price not computed at some fixed rate?
Because the rate is your input. The tool forecasts nothing; it converts what you type. In practice use a conservative rate for the quotation's validity window rather than today's mid-market, and keep the buffer for yourself.
Is the ex-works price with or without VAT?
Pick one and stay consistent. A 13% VAT-inclusive ex-works price differs by 13% from the net price, and exports are usually rebated, so FOB is normally built on net cost plus rebate impact. Mixing the two conventions is the single most common quoting mistake.