Machine Hour Rate Calculator
That "USD 12 per machine hour" on a quotation is not a guess: it is the annual cost of owning the machine divided by the hours it actually runs. This tool splits the rate into depreciation, maintenance, floor space, power, labour and overhead, so you can see which line drives the price.
| Depreciation | — CNY/h |
| Maintenance | — CNY/h |
| Floor space | — CNY/h |
| Power | — CNY/h |
| Operators | — CNY/h |
| Overhead | — CNY/h |
| Annual cost of ownership | — 10k CNY |
| Machine cost per part | — CNY |
| Parts per hour | — parts |
| Rate at 20% fewer hours | — CNY/h |
| Depreciation / labour share | —% / —% |
Accuracy ±15%. Every input here is the factory's own bookkeeping. The real error is in the hours denominator: shops that divide by calendar hours instead of running hours understate the rate by more than half. Costs only — no SG&A, no profit.
The formula
depreciation = price × (1 − salvage) ÷ life ÷ available hours
maintenance = price × maintenance rate ÷ available hours
floor = area × rent × 12 ÷ available hours
power = connected kW × load × electricity price
labour = operators × loaded hourly rate
direct = sum of the five lines above
rate/hour = direct × (1 + overhead rate)
cost/part = rate/hour ÷ (3600 ÷ cycle seconds) Nobody argues about the formula; the argument is about available hours. A single 8-hour shift over 250 days is 2,000 hours. Two shifts is 4,000. Three shifts plus Saturdays is 6,000 and already tight. Subtract changeovers, waiting for material, maintenance and scrap, and most CNC shops really run 2,500–3,500 hours a year. Moving the denominator from 2,000 to 3,000 cuts the depreciation line by a third at once.
Worked example
A 500,000 CNY machining centre, 10-year life, 10% salvage, 4,000 available hours, 3% maintenance, 20 m² at 30 CNY/m²/month, 15 kW at 60% load and 0.8 CNY/kWh, half an operator at 60 CNY/hour, 15% overhead:
| Depreciation | 45,000 ÷ 4,000 = 11.25 CNY/h |
| Maintenance | 15,000 ÷ 4,000 = 3.75 CNY/h |
| Floor space | 20 × 30 × 12 = 7,200 ÷ 4,000 = 1.80 CNY/h |
| Power | 15 × 0.6 × 0.8 = 7.20 CNY/h |
| Labour | 0.5 × 60 = 30.00 CNY/h |
| Direct cost | 54.00 CNY/h |
| With 15% overhead | 62.10 CNY/h |
| 240 s cycle (15 parts/hour) | 4.14 CNY machine cost per part |
| Hours down to 3,200 | rate rises to 66.93 CNY/h (+7.8%) |
Labour is 48% of the rate. On a semi-automatic machine the person costs more than the iron: halving the operator share from 0.5 to 0.25 drops the rate from 62.10 to 53.10 CNY/h — usually a bigger saving than buying a faster spindle.
Where to use the number
- Feed it into the CNC machining cost calculator or the moulding cost calculator to get a per-part figure.
- Compare with the rate a supplier quotes: a gap over 30% means either newer equipment or overhead hidden in the machine rate.
- Decide between a new machine and the old one: same formula, two machines, compare cost per part.
- Price idle capacity: depreciation, floor and maintenance keep running. The annual cost of ownership is the bill for a year of standing still.
Common mistakes
- Using 8,760 hours as the denominator — that halves depreciation and guarantees a loss.
- Leaving out labour — on semi-automatic equipment it is often the largest line.
- Billing power at nameplate — spindles rarely run fully loaded; 50–70% is realistic.
- Forgetting overhead — quality, facilities, maintenance staff and indirect labour all get paid.
- Baking profit into the rate — that belongs to the quotation, not the cost model.
Not included
- Tooling, fixtures and coolant (see the CNC machining calculator)
- Interest and capital charge on leased or financed equipment
- Time-of-use tariffs and demand charges
- Overhauls, relocation and re-installation
- Selling costs, profit and tax
FAQ
How do I enter a used machine?
Use the price you actually paid, a remaining life of 5–8 years and a higher maintenance rate (5–8%) — used machines fail more often and spare parts cost more.
Should I charge rent on a building I own?
Yes. The building is not free: enter "area × construction cost ÷ life" as the implied rent. Skipping it systematically understates the cost of in-house work and leads to wrong make-or-buy decisions.
How do I model one operator running several machines?
Use a fraction: 0.5 for one operator on two machines, 0.33 for three. It is an average — peaks from tool changes and alarms mean yield and OEE fall as the ratio grows.