CostKit

Stamping Cost Calculator

Estimate the per-part cost of a blanked or progressive-die stamped part: material at real coil utilization, press time, die amortisation and secondary operations. Use it to see whether a stamping quote is dominated by material, by press time, or by a die spread over too few parts.

¥— per part
Material
—
Press time
—
Die amortisation
—
Secondary ops
—

Blank weight — g · machine time — min/part · output — parts/hour

Error range ±30%. Material is charged at blank area divided by coil utilization; the real figure depends on part shape, strip width and pitch. Stroke rate assumes a running continuous press — reduce it by 30–50% for hand-fed lines. Welding, assembly, surface treatment, packing and margin are not included.

How the cost is built up

Formulas

blank weight (g) = blank area × thickness / 10 × density
material         = weight / 1000 × price ÷ utilization ÷ (1 − scrap)

strokes per part = 1 ÷ parts per stroke
machine minutes  = strokes per part ÷ stroke rate + setup ÷ batch
press cost       = minutes / 60 × press rate

die amortisation = die cost ÷ die life × strokes per part
total            = material + press + die + secondary

Worked example

SPCC 1.0 mm, 300 cm² blank, 75% utilization, 60 strokes/min, 1 part per stroke, ¥80/hour, 30 min setup over 5,000 parts, ¥50,000 die over 500,000 strokes, ¥0.20 secondary:

Material (235.5 g ÷ 75% ÷ 99.5%)¥1.89
Press time (0.0227 min/part)¥0.03
Die amortisation (¥0.10 per stroke)¥0.10
Secondary operations¥0.20
Total¥2.22 per part

Material is 85% of this part. Stamping is fast — one part per second — so almost all the cost sits in the coil. When you negotiate, argue about utilization and strip width before you argue about the die: at 5,000 parts the tooling is only 5% of the price.

Stamping versus laser cutting and bending

For small quantities, simple shapes and folded brackets, laser cutting plus bending usually wins: no tooling, and design changes do not touch a die. Above a few thousand parts, for flat blanked parts, or where dimensional consistency and surface appearance matter, stamping's material yield and cycle time push the unit cost below half of the laser route. The rough break-even is die cost divided by the saving per part — below that volume, do not cut a die.

Not included

Common questions

What utilization should I enter?

80–85% for regular shapes on a progressive die with matching strip width; 65–75% for irregular parts, multi-row layouts and large cut-outs; 50–60% for small parts punched from a wide coil. If you do not know, use 70% and treat it as the first suspect when quotes differ.

How do I estimate stroke rate?

High-speed presses run 200–600 strokes/min, conventional open-frame presses 40–80, hand-fed lines 15–30 including loading. On a progressive die the stroke rate is the strip index rate, and each stroke produces one or several parts.

Is 500,000 strokes a normal die life?

For cold-rolled mild steel, regrinding every few tens of thousands of strokes and a total life of 300,000–1,000,000 strokes is typical. Stainless and aluminium wear dies faster; carbide tooling reaches millions of strokes at several times the die cost.

Why is a small-quantity quote so high?

Because the die is spread over the strokes actually run. ¥50,000 over 5,000 parts is ¥10 each; over 50,000 parts it is ¥1. The gap between two quotes is often not material at all, but the batch size and die life the supplier assumed.