CostKit

Stamping Die Cost Estimator

The stamping cost calculator takes tooling cost as an input, but a quotation rarely tells you what a die is worth beyond the words "one set". This tool fills that gap: from blank size and station count it splits a tool into die set, working steel, machining hours and tryout, so you can tell whether a tooling quote is in the right order of magnitude before you negotiate.

1. Inputs

¥ — per die set
Die set (plates, guide pins and bushes)— CNY
Working steel— CNY
Machining and assembly— CNY
Tryout and tuning— CNY
Die working area (50 mm margin included)— cm²
Total machining hours— h
Combined factor (type × precision × volume)— ×

±35%. Tooling is quoted, not computed: the same drawing differs twofold between regions, suppliers and whether design is in-house. Use this to place a quote in the right order of magnitude and to see which line item eats the budget — not to argue a supplier down to the yuan.

Formula

die area (cm²)     = (blank length + 100) × (blank width + 100) ÷ 100
die set (CNY)      = 2500 + 5 × die area
steel (kg)         = die area × 4.0 cm × 7.85 g/cm³ ÷ 1000
steel (CNY)        = steel kg × 28
hours per station  = 40 + 0.12 × die area^0.8
machining (CNY)    = hours per station × stations × 200
tryout (CNY)       = stations × 2 passes × 4 h × 400 CNY/h
total (CNY)        = (die set + steel + machining + tryout)
                     × type × precision × volume factor

The 100 mm added to each dimension is the 50 mm margin a die set needs on all four sides. The power term 0.12 × area0.8 says that machining hours grow slower than area: a large die is cut in one setup on a gantry mill, while a small one spends a larger share of its time on clamping and edge finding.

What each input means

Worked example

300 × 200 mm blank, 3-station progressive die, medium volume, standard precision (the page defaults):

Die area(300+100) × (200+100) ÷ 100 = 1200 cm²
Die set2500 + 5 × 1200 = 8,500 CNY
Working steel1200 × 4 × 7.85 ÷ 1000 = 37.68 kg → × 28 = 1,055 CNY
Hours per station40 + 0.12 × 12000.8 = 40 + 34.88 = 74.88 h
Machining74.88 × 3 × 200 = 44,926 CNY
Tryout3 × 2 × 4 × 400 = 9,600 CNY
Subtotal8,500 + 1,055 + 44,926 + 9,600 = 64,081 CNY
Total64,081 × 1.25 = ¥80,101

Varying one condition at a time, with everything else unchanged:

Single-operation die, low volume64,081 × 1.00 × 0.90 = ¥57,673
Precision class, high volume64,081 × 1.25 × 1.25 × 1.20 = ¥120,151
3 → 5 stationsmachining 74.88 × 5 × 200 = 74,876; tryout 16,000; subtotal 100,431 → ¥125,539

Note the second row: precision and volume multiply the whole subtotal, not just the steel. In reality precision shows up mostly in machining hours and volume mostly in steel and heat treatment — the factor method is deliberately coarse. Do not use it as a line-item cost sheet.

Four mistakes that skew the number

Not included

FAQ

Why is a progressive die dearer at the same station count?

Because it packs N operations into one die set: plates must be thicker for rigidity, the strip feed needs accurate pitch, every station needs lifters and pilots, and assembly and tuning grow faster than station count. The extra 25% buys one press, one setup and a stable cycle — at volume that saves more press hours than the tool difference.

Why is the station count capped at 12?

Beyond roughly 12 stations the part usually should not be run in a single progressive tool, or it needs splitting across two dies in sequence. The cap keeps the estimate inside the range where the model is still meaningful; forcing the formula past it produces numbers nobody should quote against.

The estimate is far from the quote I received. Which is right?

Look at which line differs. Die sets are standard parts with transparent pricing, so the gap is usually in machining hours and steel grade. If the quote is more than double, ask whether it includes carbide, nitrogen springs or automatic feeding. If it is half, check die life and after-sales — cheap tooling shows its real cost during production, not at PO.