CostKit

Blow Mould Cost Estimator

The blow moulding cost calculator takes "blow mould cost" as an input — but quotes usually just say "one mould". This tool answers what that means: by part volume and cavity count it splits the cavity block, frame, neck inserts, handle insert, cooling circuits and trial shots, applies a material and output-tier factor, and returns cost per shot so you can paste it back into the part cost calculator.

1. Inputs

Use the nominal capacity; wall thickness and flash make the cavity slightly bigger (a 1 L bottle runs 1.05–1.15 L).
<100k ×0.95, 100k–1M ×1.00, >1M ×1.12.

¥ — per mould
Cavity block (roughing, cavity surface, parting line fitting)— CNY
Frame / base plate / guide pins— CNY
Neck inserts (per cavity)— CNY
Handle insert— CNY
Cooling circuits (drilling, plugs, pressure test)— CNY
Trial shots (machine time)— CNY
Cavity factor— ×
Combined factor (material × output tier)— ×
Cost per shot (total ÷ reference life)— CNY/shot
Reference life of this material— shots

Put "cost per shot" into the blow moulding cost calculator (mould cost ÷ life) to get this mould's contribution to the unit cost. Life is the material reference value; real life also depends on cooling water quality and colour changes.

±35%. Blow moulds are quoted discretely: the same 1 L bottle can differ by 50–100% between north and south China, between a cosmetics-bottle shop and a jerry-can shop, with or without flow analysis and quick-change hardware. Use this to check the order of magnitude and to see which line eats the budget — not to argue a quote down to the cent.

Formulas

cavity factor     = 1 + 0.55 × (cavities − 1)
cavity block(CNY) = (11250 + 6750 × volume L) × cavity factor
frame(CNY)        = (3000 + 900 × volume L) × (1 + 0.25 × (cavities − 1))
neck inserts(CNY) = 1500 × cavities            (only when ticked)
handle insert(CNY)= 2200                       (only when ticked)
cooling(CNY)      = 800 + 400 × volume L
trial shots(CNY)  = 3 × 2 h × 400 CNY/h = 2400
total(CNY)        = sum of six lines × material factor × output tier factor
per shot(CNY)     = total ÷ reference life (300k / 750k / 1M shots)

Why volume rather than area or perimeter? A blow mould is hogged out: the cavity is a half-bottle dug into a block, so bigger volume means a thicker blank, more roughing and longer cooling circuits. Stamping dies scale with area, extrusion dies with perimeter — pick the wrong basis and the estimate is off by an order of magnitude. A flat shampoo bottle and a slim water bottle of the same 1 L differ by less than 20%, because the removed volume is nearly identical.

What the inputs mean

Worked examples

1 L bottle, single cavity, aluminium, neck insert, no handle, 300k pcs/year (page defaults):

Cavity factor1 + 0.55 × 0 = 1.00
Cavity block(11250 + 6750 × 1) × 1.00 = 18,000 CNY
Frame(3000 + 900 × 1) × 1 = 3,900 CNY
Neck insert1500 × 1 = 1,500 CNY
Cooling800 + 400 × 1 = 1,200 CNY
Trial shots3 × 2 × 400 = 2,400 CNY
Subtotal18,000 + 3,900 + 1,500 + 1,200 + 2,400 = 27,000 CNY
Total27,000 × (1.00 × 1.00) = ¥27,000
Per shot27,000 ÷ 300,000 = ¥0.09/shot

Same formulas with other conditions:

5 L chemical drum, 2 cavities, tool steel, neck + handle, 2M pcs/year block 45,000 × 1.55 = 69,750; frame 7,500 × 1.25 = 9,375; neck 3,000; handle 2,200; cooling 2,800; trial 2,400 → 89,525 × (1.90 × 1.12 = 2.128) = ¥190,509, ¥0.19/shot
0.5 L bottle, 4 cavities, beryllium copper, neck insert, no handle, 50k pcs/year block 14,625 × 2.65 = 38,756.25; frame 3,450 × 1.75 = 6,037.50; neck 6,000; cooling 1,000; trial 2,400 → 54,193.75 × (1.55 × 0.95 = 1.4725) = ¥79,800, ¥0.11/shot
Drop the handle insert from the 5 L drum 89,525 − 2,200 = 87,325 × 2.128 = ¥185,828 (saves ¥4,681)

Note the second row: a 0.5 L bottle costs nearly three times a 1 L one — not because of size, but because of 4 cavities + beryllium copper (2.65 × 1.55). Conversely, if a quote for a 0.5 L bottle lands near a single-cavity 1 L price, suspect a single-cavity mould — you would get a quarter of the output.

Four common mistakes

Not included

FAQ

Why is a 2-cavity mould not twice a 1-cavity one?

Because the expensive shared parts — frame, base plate, guides, cooling circuits, trial labour and machine time — cost almost the same for one or two cavities. What doubles is the cavity block and the neck inserts. The 1.55 factor approximates this; past 4 cavities the shared share shrinks and the factor under-estimates, which is why the tool stops at 4.

Aluminium versus tool steel differs by 90% — why?

Life and cooling. Aluminium conducts roughly 150 W/(m·K) against ~30 for tool steel: faster cooling, shorter cycles, but lower hardness, so cavity surfaces scuff after a few hundred thousand shots. Steel reaches a million shots and wins on cost per shot. Decide on total volume: aluminium below 300k parts, steel above 1M, and in between by whether transparency and appearance matter.

The estimate differs a lot from the quote — whom do I trust?

Locate the line that differs. Frame and cooling are fairly transparent; the gap usually sits in cavity machining time and steel grade. If the quote is more than double, ask about flow analysis, imported steel and wall control. If it is half, check cavity count and material — the usual way to cheapen a blow mould is fewer cavities and recycled aluminium, and the money comes back in cycle time and repairs.