Die Casting Mould Cost Estimator

The die casting cost calculator takes "mould cost" and "mould life" as inputs — but quotes just say "tooling included". This tool answers what that money is: from projected area and shot pressure it picks the machine tonnage bracket, then splits frame, cavity machining, slides, vacuum system and trial shots, applies steel and annual-volume factors, and returns cost per shot to paste straight back into the part cost page.

1. Inputs

For aluminium the runners, overflow and vents add 15%–35%; using the net area understates the tonnage by one bracket.
Zinc 40 / magnesium 50 / aluminium standard wall 60 / thin-wall large part 80 / leak-tight 90.
Each slide is 9% of frame + cavity, covering slide base, angle pin and locking block.
<30k ×0.95, 30k–300k ×1.00, >300k ×1.15.

¥ — per die
Selected machine tonnage— t
Design clamp force (incl. 1.15 safety)— kN
Frame / base plate / guide pins / ejector— CNY
Cavity machining (roughing, cavity surface, parting line)— CNY
Slides / side-core mechanisms— CNY
Vacuum system interface— CNY
Trial shots (machine time)— CNY
Cavity factor— ×
Combined factor (steel × volume tier)— ×
Cost per shot (total ÷ reference life)— CNY/shot
Reference life of this steel— shots

Put "cost per shot" and the reference life into the die casting cost calculator to get this tool's contribution to the unit cost. Life is a steel reference value; preheating, coatings and melt temperature control move it a lot.

±35%. Die casting tools are quoted discretely: the same 200 t die can differ by 40–80% depending on whether CAE is included, whether slides are made in-house or outsourced, and whether the cavity is nitrided or coated. This tool gives the order of magnitude and shows which line item eats the budget. Do not use it to argue a quote down to the cent — use it to point out the part that is clearly off.

Formula

total area (cm²)  = projected area per part × cavities
design clamp (kN) = total area × pressure (MPa) × 0.1 × 1.15
machine tonnage   = first standard bracket with tonnage × 9.80665 ≥ design clamp
cavity factor     = 1 + 0.55 × (cavities − 1)
frame (CNY)       = (10000 + 100 × tonnage) × (1 + 0.15 × (cavities − 1))
cavity (CNY)      = 900 × projected area^0.8 × cavity factor
slides (CNY)      = 0.09 × (frame + cavity) × number of slides
vacuum (CNY)      = 6000                      (only if ticked)
trial shots (CNY) = 3 runs × 3 h × (150 + 0.6 × tonnage) CNY/h
total (CNY)       = sum of five items × steel factor × volume-tier factor
per shot (CNY)    = total ÷ reference life (80k / 120k / 200k shots)

Why price a die casting tool by tonnage rather than area, volume or perimeter? The die has to fit between the tie bars: frame size, plate thickness, guide pin diameter and ejector layout all follow the machine tonnage. The same 120 cm² cavity on a 160 t and an 800 t machine sits in frames whose weight differs three- or four-fold. Area drives the cavity item; tonnage drives the frame item. Keeping them separate is what stops a small part being quoted at a large-part price.

What the inputs mean

Worked example

Projected area 120 cm², 2 cavities, 60 MPa, H13, one slide, no vacuum, 100k shots/year (page defaults):

Total area120 × 2 = 240 cm²
Design clamp force240 × 60 × 0.1 = 1,440 kN, × 1.15 = 1,656 kN
Machine tonnage1,656 ÷ 9.80665 = 168.9 t → 200 t (160 t only gives 1,569 kN)
Cavity factor1 + 0.55 × 1 = 1.55
Frame(10,000 + 100 × 200) × 1.15 = 34,500 CNY
Cavity machining900 × 120^0.8 × 1.55 = 900 × 46.0622 × 1.55 = 64,256.82 CNY
Slides0.09 × (34,500 + 64,256.82) × 1 = 8,888.11 CNY
Trial shots3 × 3 × (150 + 0.6 × 200) = 9 × 270 = 2,430 CNY
Subtotal34,500 + 64,256.82 + 8,888.11 + 2,430 = 110,074.93 CNY
Total110,074.93 × (1.00 × 1.00) = ¥110,074.93
Per shot110,074.93 ÷ 80,000 = ¥1.38/shot

Same formula, different conditions:

500 cm² single cavity, thin wall 80 MPa, SKD61, no slides, vacuum, 400k shots/year Design 4,600 kN → 500 t; frame (10,000 + 50,000) = 60,000; cavity 900 × 144.27 = 129,842.99; vacuum 6,000; trials 9 × 450 = 4,050 → 199,892.99 × (1.15 × 1.15 = 1.3225) = ¥264,358.48, ¥2.20/shot
30 cm² zinc part, 4 cavities, 40 MPa, H13, no slides, no vacuum, 20k shots/year Design 552 kN → 160 t; frame 26,000 × 1.45 = 37,700; cavity 900 × 15.1949 × 2.65 = 36,239.77; trials 9 × 246 = 2,214 → 76,153.77 × 0.95 = ¥72,346.08, ¥0.90/shot
Default case with three slides instead of one Slides 8,888.11 × 3 = 26,664.34 → ¥127,851.16 (¥17,776 more)

The first row is worth pausing on: a 500 cm² single-cavity die costs 2.4× the default case, not because the area is four times larger, but because the bracket jumps from 200 t to 500 t — frame and trial-shot machine time jump with it, and vacuum plus the higher volume factor stack on top. Conversely, if a 500 cm² part is quoted near the price of a 200 t die, check the cavity count and whether vacuum and slides were quietly dropped.

Four common mistakes

Not included

FAQ

Why compute tonnage first instead of pricing directly from area?

Because the frame is priced by tonnage, not by area. A die casting frame carries the clamp force and the shot impact: plate thickness, guide pin diameter and ejection force are all sized to the machine. The same 120 cm² cavity on a 160 t and an 800 t machine can sit in frames whose weight differs more than three-fold. Pricing "area × rate" overquotes small parts, underquotes large ones, and the error has no consistent direction.

H13 versus SKD61: is the 15% worth it?

It depends on total shots and surface requirements. They are the same family of hot-work tool steel; the difference is melt cleanliness and heat-treat stability. SKD61 resists heat checking better, so the cavity surface does not craze early. Above roughly 100k shots a year, or for visible surfaces, the extra 15% is usually repaid by one fewer repair; for prototype and small batches it is not.

The estimate and the toolmaker's quote differ a lot — which do I trust?

Look at which line differs. Frame steel weight and machining are fairly transparent; the gap usually sits in cavity machining hours, slide count and steel grade. If the quote is more than double, ask whether CAE, imported steel or outsourced slides are included. If it is half, check the tonnage bracket, cavity count and vacuum — the classic way to make a die casting tool "cheap" is to squeeze the cavity into a smaller frame, and the money comes back as flash, distortion and repairs in production.

References

  1. Castings — General dimensional and geometrical tolerances and machining allowances ISO · ISO 8062-3
  2. Product Standards for Die Castings NADCA · NADCA #401
  3. Non-ferrous metal spot prices SMM · 公开行情

Basis for the parameters above. Links go to the publisher or its search page; the standard text itself is sold by the publisher. Price references are public market ranges, not supplier quotations.